Generation of Business Process Reference Model Considering Multiple Objectives
  • 비영리 CC BY-NC
  • 비영리 CC BY-NC
ABSTRACT
Generation of Business Process Reference Model Considering Multiple Objectives
KEYWORD
Business Process Management , Business Process Reference Model , Multi-Objective , Genetic Algorithm
  • 1. INTRODUCTION

    It is a common practice to customize processes from reference processes or templates in order to reduce the time and effort required to design and deploy processes on all levels (Lu and Sadiq, 2006). In order to address redundancy and underutilization problems, a generic process model, called as business process (BP) reference, is absolutely necessary to cover the best of process variants. Industrial process model collections and reference process models (e.g., ITIL, SCOR, eTOM) are some related concepts, practices and standards for developing such a process model. However, those concepts are settled as a high-level model without considering the customization implementation. Customization is a major trend that occurs in many industries and markets resulting from the customer’s specific demand on goods and services.

    The notion of BP variant is important in explaining the customization in this study. We use the terminology of BP variant to represent the different kind of customized BP with almost similar business objectives. For example, a supplier offers, specifies, produces and delivers different kinds of products to its customers, or suppliers have different kinds of actor relationships that separate orders and frame contracting. Due to the different kinds of BP, there will be a problem in resolving which process is appropriate to a given organization. The difficulty derives from the fact that the activities involved in taking an account to contribute in two or more than hundreds of process. It is certain that a “good” process should be obtained. In order to obtain a “good” process, it is necessary to find a generic process, later called as reference model, that considers a part of sequential view of process with an understanding of the business properties included in the activity.

    Approaches to the generation of BP reference models have been explored. Previous work on BP reference model generation has utilized proximity score measurement (PSM) and dealt with activity proximity and frequency as well as validity (Yahya et al., 2010). A reference model with only a single alternative solution is equally unsatisfactory to stakeholder. Cost and duration, indeed, are two additional important factors relevant to business objectives. In contrast to the single-objective case, a multi-objective approach can be used to simultaneously optimize, subject to certain constraints, two or more conflicting objectives so as to find a valid and representative BP reference model. Multi-objective optimization is the process of simultaneously optimizing two or more conflicting objectives subject to certain constraints. By using multi-objective optimization, it may bring some advantages in finding a valid and representative BP reference models compared with single objective problem.

    This study presents a method of solving the multi-objective optimization problem by using forms of genetic algorithms. In multi-objective genetic algorithms we attempt to optimize not only one fitness parameter but also a collection of them. To achieve this, we generate a method of measuring the overall fitness of the set of objectives.

    This paper is organized as follows. Section 2 discusses works related to this study. The proposed approach is described in Section 3. The result of experiments is presented in Section 4 and Section 5 concludes this study.

    2. LITERATURE REVIEW

    Many efforts have been made on BP modeling research and research on finding reference BP based on BP models is on the increase. van der Aalst et al. (2005) discussed configurable process models as a basis for reference modeling. Li et al. (2009) extended previous research by proposing a heuristic approach to discovering reference models using a measurement to analyze the distance of change operations in modeling. It updates process configurations and produces new reference models based on a minimum edit distance from initial reference processes. A mathematical programming approach to discovering new reference models was introduced to address the issue of creating reference processes without initial reference information or process reconfiguration. There remain problems in the presentational and validation aspects of the process using interger programming formulations, which this study attempttted to overcome with a genetic algorithm approach in (Yahya et al., 2010).

    Multi-objective genetic algorithms (MOGA) have been widely used in many areas including order allocation (Wu et al., 2012), scheduling problem (Zinflou et al., 2008; Minella et al., 2008), human resource planning (Abboud et al., 1998; Hajri-Gabouj, 2003) or design and planning problem (Zhou et al., 2003; Gen et al., 2009). Deb et al. (2002) used genetic algorithm to solve multi-objective problems and develop non-dominated sorting and further brought up the idea of using the elitist strategy may have a better convergence when using the genetic algorithm (GA). Research using GA on graph topology is limited to supply chain network (Wang et al., 2010). Hence, this study proposes a novel approach on BP modeling domain.

    In the domain of BP, Quan and Tian (2009) presented a research on business processes’ multi-objective optimization to point out at three criteria of variables: processing time, process cost, and quality. The proposed research used simulation as the result experiments. Vergidis et al. (2006, 2007) carried out researches on BP improvement using multi-objective optimization and composite BP using an approach of evolutionary multi-objective optimization approach. Neubauer and Heurix (2008a, 2008b) discussed a case study a multi-objective decision support for defining secure BP. However, none of those studies point out variables related to the process structure behavior which is one of the important aspects on generating reference model.

    3. PROPOSED APPROACH

       3.1 Mixed-Integer Linear Programming Model

    This section provides definitions of process model and structural schema to describe a formal model of BP.

    Definition 1 (Process model).

    We define a process model pk as the k-th process in a process repository. It can be represented as a tuple of <Ak, Lk>, each element of which is defined below.

    Ak = {ai| i = 1, …, I} is a set of activities where ai is the i-th activity of pk and I is the total number of activities in pk.

    A is defined as a set of all activities in the process repository, where A is the union of all Ak,

    image

    Lk ⊆{lij = (ai, aj) | ai, aj ∈Ak } is a set of links where lij is the link between two activities ai and aj in the k-th process. The element (ai, aj) represents the fact that ai immediately precedes aj.

    ai+ is the activity following ai and ai- is the activity preceding ai

    L is a set of all links in the process repository, where L is the union of all Lk, k = 1, …, K, i.e.,

    image

    For a split activity ai, such that |Ni| > 1, where Ni = {aj+ |(ai,ai+)∈L}, f(ai+) = ‘AND’ if all ai+ should be executed; otherwise, f(ai+) = ‘XOR.’

    For a merge activity ai, such that |Mi| > 1, where Mi = {aj-|(ai-, ai) ∈ L}, f(ai-) = ‘AND’ if all ai- should be executed; otherwise, f(ai-) = ‘XOR.’

    In order to collect information on the variety of start and end activities among process variants, we define AS and AE as the sets of start and end activities, respectively.

    AS = {ai| ai ∈ Ak, |Mi| = 0, ∀k ∈ K} is a set of start activities in all K process variants where ai is an activity in pk with an empty set of preceding activities, |Mi| = 0.

    AE = {ai| ai ∈ Ak, |Ni| = 0, ∀k ∈ K} is a set of end activities in all K process variants where ai is an activity in pk with an empty set of succeeding activities, |Ni| = 0.

    Definition 2 (Structural flow schema).

    A structural schema is a set of tuples, each of which has an index and link information. A structural schema (H) required for the chromosome generation is defined as

    H = {(s, lij) | s = 1, 2, …, S, and lij ∈ L}

    The value of s will start from 1 and increase accordingly until all links are assigned. The value of s increases in different ways according to control flow types, sequential flow and split-merge flow. For each lij in a sequential flow, increasing number of s will be assigned, and each lij has a unique integer value of s. For all lij’s from a split activity or to a merge activity, a single value of s will be assigned.

    Index and subscript

    K : the number of process variants

    K : process variant index, k = 1, …, K

    S : structural flow schema index, s = 1, …, S

    i, j, r, t : activity index

    Set

    pk : process k in a process repository

    Ak : a set of activities in process k

    Lk : a set of links in process k

    A : a set of all activities in the process repository

    AS : a set of start activities among K processes

    AE : a set of end activities among K processes

    L : a set of all links in the process repository

    H : a set of structural flow schema in a group of process variants

    Pi : a set of immediately preceding activities (predecessors) of activity i in the process repository

    Si : a set of immediately succeeding activities (successors) of activity i in the process repository

    Parameter

    Ci : expected cost to execute i-th activity

    Cij : proximity score for executing a link (ai, aj) (∈ L)

    Ei : expected time to execute i-th activity

    Ni : number of predecessors of i-th activity

    Mi : number of successors of i-th activity

    Vs : coordination time between activities in schemes.

    Ws : average coordination time.

    image

    (derived from average duration divided by number of links in one structural scheme)

    M : big M, a very large positive

    ri : ready time for i-th activity

    fi : finish time for i-th activity. Particularly, fi = ri+Ei

    Decision variable

    vi : equals to 1 if activity is selected, ai ∈ A; 0, otherwise

    yi : equals to 1 if activity ai ∈ AS is a start activity and an element of the set of start activities; 0, otherwise

    zi : equals to 1 if activity ai ∈ AE is an end activity and an element of the set of end activities; 0, otherwise

    image

    : equals to 1 if activity ai immediately precedes activity aj in scheme s, (ai, aj) ∈ L, (s, lij) ∈H; 0, otherwise

    image
    image
    image

    Note that a tri-objective integer programming model for generating a BP reference model is provided as an extension of a single objective problem. First, it attempts to find the maximum proximity score, (notice that it has been converted into a minimization problem), among the links existing in the process variants. The BP reference should satisfy the business requirements, which are defined as duration (2) and cost (3). Activity duration, called makespan, is a measure to evaluate the expected execution time of a BP reference model. In respect to cost, it will sum the costs of all selected activities for the best BP reference model.

    In particular, the constraint can be decomposed into four segments; scheme (4)-(5), predecessors (6)-(9), successors (10)-(13), and predefined duration (14)-(16), respectively. Scheme constraint (4) specifies that a scheme behavioral relation of an activity should be less than or equal to 1. Among all structural schema relations, it should be a scheme that is consistent with (5). With regard to predecessors, constraint (6) expresses that there should be at least one link entering activity i if activity i exists and activity i is not a start activity. To find a start activity, there should be a constraint to certify that there are no immediate predecessors to activity i (7). Certainly, activity consistency constraint (8) is necessary, that is, that an (start) activity is selected in the BP reference. In addition, we apply constraint (9) to specify that only an activity from a set of start activities (AS) can be a start activity, thereby restricting others (10).

    Constraints

    image
    image
    image
    image
    image
    image
    image
    image
    image
    image
    image
    image
    image
    image
    image
    image
    image

    Subsequently, with regard to successors, constraint (11) expresses that there should be at least a link leaving activity i if activity i exists and activity i is not an end activity. To find an end activity, there should be a constraint to certify that there are no immediate successors to activity i (12). Certainly, we need to apply activity consistency constraint (13) to ensure that an (end) activity is selected in the BP reference. In addition, we set constraint (14) to specify that an activity can be an end activity only if it is from a set of end activities (AE), and restrict, thereby, others (15).

    Constraints (16)-(19) relate to process duration. Constraint (16) denotes that the ready time of activity j should be greater or the same as the finish time of activity I, including the coordination time and the average duration that may occur during split or merge. Constraint (17) defines the relations among ready time, execution time and finish time. Constraint (18) specifies the makespan. Constraint (19) ensures that the adjacent relationship of activities i and j includes a binary value element. Constraint (20) specifies that all activities (including start and end activities) has a binary value element.

       3.2 Multiple-Objective BP Genetic Algorithm

    This section proposes a solution to the BP reference selection problem, using a multi-objective genetic algorithm with maximizing proximity score measurement, cost minimization and duration minimization objectives (MOBPGA). MOBPGA considers four parameters, including generation size (gen_size), population size (pop_size), crossover rate (r1), and mutation rate (r2) (Gen and Cheng, 2000). The generation, denoted by t, represents the number of computation iterations of the GA. It contains a set of solutions that collectively corresponds to a population, denoted as P(t). Chromosomes, which represent the solution, consist of genes that encode genotypes for evolution, and should be evaluated based on specific measures of fitness during each generation. In order to generate new offspring O(t), a new generation of chromosomes, MOBPGA employs crossover and mutation operations.

    Procedure: Multi-objective business process genetic algorithm (MOBPGA)

    begin

    initialize P(t);

    evaluate P(t) based on the NSGAII;

    generate Pareto solutions;

    for t = 1 to gen_size do

    recombine P(t) to yield O(t) based on the partial- mapped crossover and random key representation mutation;

    evaluate O(t) based on the NSGAII;

    update Pareto solutions;

    select P(t+1) from P(t) and O(t) based on the composite Pareto ranking selection (cPrs);

    end

    end

    The MOBPGA begins with initialization and ends when the number of run generations reaches the generation size. Following several generations of evolution, the algorithms improve solution quality and, in some cases, converge to the optimal solutions of the problem. Increasing the population size, generation size, crossover rate, or mutation rate explores more of the solution space while requiring greater computational effort. The final decision is made by the decision makers, who manually select the preferred Pareto solution according to their preference structures.

    The proposed MOBPGA includes specific random key representation for encoding and decoding, partially mapped crossover, random key representation mutation, an algorithm for efficient Pareto sorting (NSGAII), and composite Pareto ranking selection (cPrs) (Goldberg, 1989). Figure 1 shows the random key representation of encoding method used in this study.

    Due to the random genetic processes (crossover and mutation) that might produce an invalid result, it is necessary to verify the process for further generation. We apply the soundness properties of business processes to verify the process well-formedness. For a business process model to be sound, three properties are required (van der Aalst, 2000): 1) for every activity aj that is reachable from ai, there exists a sequence to the next activity until a preferred end activity aE is reached, 2) a preferred end activity aE is the activity that should be reachable from a start activity aS, and 3) there is no activity that is never processed in any execution of the model (there are no needless elements).

    In order to generate a valid BP, there should be a decoding mechanism that follows some procedures. In this approach, there are three important mechanisms of decoding mechanism for establishing a valid BP. First, it checks the start and end activity. Second, it should check the scheme (mapping processes and links). Finally, it will check the path which contains candidate links. There are four steps to execute the decoding mechanism which is as follow.

    Step 1: Disqualify schemes flowing to Start of flowing from End.

    Step 2: Disqualify pair of activities that are not existed in the repository

    Step 3: Disqualify activities that are not available in the path

    Step 4: Restructure feasible activities and schemes

    4. EXPERIMENT RESULTS

    In order to validate our approach, several experiments were conducted. The experiment estimates the validity of the proposed algorithm in real settings by using logistics processes that contain a various types of process structure. Numerical analysis was performed on a desktop computer equipped with an Intel® Pentium® D 3.40GHz CPU and 2GB RAM. The commercial software LINGO 11.0 (LINGO System) was used to generate a reference set of non-dominated solutions, R, utilizing embedded integer programming (IP) packages. For each scenario, LINGO solved the weighted-sums problem with objectives (1)-(3) subject to (4)-(20), which was recognized as ILP (shown in Lingo) and terminated at local optimal solutions. For each problem instance, a local optimal solution was collected within various ranges of computation time. Hence, each scenario has a set of non-dominated solutions for further comparison. The performance metrics discussed above were used to compare the performances of MOBPGA and multi-objective mixed integer linear programming (MoMILP).

    We conducted an experiment with various numbers of activities among four process groups (PG). Four groups from PG-I to PG-IV, each consisting of ten process variants (p1p10), were formed. Process variants are generated from a single process model, each of which fits a certain scenario and context; in other words, the configuration of a particular process variant reflects the specific requirement and circumstance of the process. The gradual increase in the number of activities of each process group is shown in Table 1. Since there is no exact cost and duration time data on our logistics process models, we express them using random integer values representing units of metric rather than real numbers for any currency or time.

    [Table 1.] Mean number of activities in each group of 4 processes

    label

    Mean number of activities in each group of 4 processes

    Based on our results using process group III (PG-III), the single-objective approach can produce only a single process reference model, with no guarantee of meeting some requirements (Figure 2). Our proposed approach has several alternatives for decision makers. For example, a process manager might want to select a BP reference model for duration of less than 30 units of time. Some of these alternative candidates are shown in Figure 3. The choice of generating given alternatives will correspond to the stakeholders’ business requirements and will accrue benefits to business organizations in terms of strategic competitiveness.

    When we applied process variants of activity number 20 (PG-IV), MoMILP computation time was intractable. Thus, we set a cut-off time of 21,600 seconds to obtain feasible solutions. The MOBPGA parameters operative were 1,000 generations, a population size of 20, a mutation rate of 0.8 and multiplier (set on 0.9) for the purpose of selection. Experiment result is shown in Table 2. The computational time of the approaches,

    MoMILP and MOBPGA, are listed in Table 3. MoMILP sets a cut-off time of 21,600 seconds for feasible solutions, compared with MOBPGA’s 222 seconds for an activity num-ber of 20. Finally, the performance of the MOBPGA is robust and our performance evaluations showed little dif-ference from MoMILP in terms of quality of the solutions.

    [Table 3.] Performance evaluations of three scenarios using MoMILP and MOBPGA

    label

    Performance evaluations of three scenarios using MoMILP and MOBPGA

    5. CONCLUSION

    This paper proposes a MOBPGA with specific random key representation of encoding and decoding to solve the problem of BP reference model generation with objective functions maximizing process proximity while minimizing cost and duration. The proposed model meets customer requirements by coordinating objectives, specifically by incorporating the process topology into the operational objectives. It also presents a compromise approach that can facilitate decision making in the context of a large set of Pareto solutions, thereby enabling decision makers to incorporate other preferences or business concerns. By utilizing the results of non-dominated solutions both from MOBPGA and MoMILP, we can suggest alternative solutions to stakeholders based on certain conditions. Compared with the conventional ap-proach, this provides more solutions to decision makers, enabling them to select process reference models based on their requirements.

    BP reference model generation will have to be improved, considering the following limitations. First, this study employed experiments using the block concept of process structure. Whereas there are some benefits on the experiments, this approach covers a little issue with regard to deadlock and flawless process in BP. Moreover, there are some issues remaining with regard to operation dependency within activities. Second, since the graph generation was assumed to be flawless, there is a need to carefully consider the control flow semantics such as AND or OR control-flow in generating the BP reference model. These are issues that will require further research.

참고문헌
  • 1. Abboud N., Inuiguchi M., Sakawa M., Uemura Y. (1998) Manpower allocation using genetic annealing [European Journal of Operational Research] Vol.111 P.405-420 google
  • 2. Deb K., Pratap A., Agarwal S., Meyarivan T. (2002) A fast and elitist multiobjective genetic algorithm: NSGA-II [IEEE Transactions on Evolutionary Computation] Vol.6 P.182-197 google
  • 3. Goldberg D. E. (1989) Genetic Algorithms in Search, Optimization, and Machine Learning google
  • 4. Gen M., Cheng R. (2000) Genetic Algorithms and Engineering Optimization google
  • 5. Gen M., Katai O., McKay B., Namatame A., Sarker R. A., Zhang B.-T. (2009) Intelligent and Evolutionary Systems google
  • 6. Hajri-Gabouj S. (2003) A fuzzy genetic multiobjective optimization algorithm for a multilevel generalized assignment problem [IEEE Transactions on Systems, Man, and Cybernetics, Part C: Applications and Reviews] Vol.33 P.214-224 google
  • 7. Li C., Reichert M., Wombacher A. (2009) Discovering reference models by mining process variants using a heuristic approach [Business Process Management, Lecture Notes in Computer Science] Vol.5701 P.344-362 google
  • 8. Lu R., Sadiq S. (2006) Managing process variants as an information resource [Business Process Management, Lecture Notes in Computer Science] Vol.4102 P.426-431 google
  • 9. Minella G., Ruiz R., Ciavotta M. (2008) A review and evaluation of multiobjective algorithms for the flowshop scheduling problem [INFORMS Journal on Computing] Vol.20 P.451-471 google
  • 10. Neubauer T., Heurix J. (2008a) Defining secure business processes with respect to multiple objectives [Proceedings of the 3rd International Conference on Availability, Reliability and Security] P.187-194 google
  • 11. Neubauer T., Heurix J. (2008b) Multiobjective decision support for defining secure business processes: a case study [International Journal of Business Intelligence and Data Mining] Vol.3 P.177-195 google
  • 12. Quan L., Tian G.-S. (2009) A business processes’ multi-objective optimization model based on simulation [Proceedings of International Conference on Information Management, Innovation Management and Industrial Engineering] P.572-575 google
  • 13. Tiwari A., Vergidis K., Turner C. (2010) Evolutionary multi-objective optimization of business processes [Soft Computing in Industrial Application, Advances in Intelligent and Soft Computing] Vol.75 P.293-301 google
  • 14. Van der Aalst W. M. P. (2000) Workflow verification: finding control-flow errors using Petri-net-based techniques [Business Process Management, Lecture Notes in Computer Science] Vol.1806 P.161-183 google
  • 15. Van der Aalst W. M. P., Alves de Medeiros A. K., Weijters A. J. M. M. (2005) Genetic process mining [Applications and Theory of Petri Nets, Lecture Notes in Computer Science] Vol.3536 P.48-69 google
  • 16. Vergidis K., Tiwari A., Majeed B. (2006) Business process improvement using multi-objective optimization [BT Technology Journal] Vol.24 P.229-235 google
  • 17. Verdigis K., Tiwari A., Majeed B., Roy R. (2007) Optimisation of business process designs: an algorithmic approach with multiple objectives [International Journal of Production Economics] Vol.109 P.105-121 google
  • 18. Wang L.-C., Cheng C.-Y., Huang L.-P. (2010) A genetic algorithm for directed graph-based supply network planning in memory module industry [Industrial Engineering and Management Systems] Vol.9 P.227-241 google cross ref
  • 19. Wu J.-Z., Chien C.-F., Gen M. (2012) Coordinating strategic outsourcing decisions for semiconductor assembly using a bi-objective genetic algorithm [International Journal of Production Research] Vol.50 P.235-260 google
  • 20. Yahya B. N., Bae H., Bae J., Kim D. (2010) Generating business process reference model using genetic algorithm [Proceedings of the 23th Annual Conference of Biomedical Fuzzy Association, Soft Computing Application] P.245-248 google
  • 21. Zhou G., Min H., Gen M. (2003) A genetic algorithm approach to the bi-criteria allocation of customers to warehouses [International Journal of Production Economics] Vol.86 P.35-45 google
  • 22. Zinflou A., Gagne C., Gravel M., Price W. L. (2008) Pareto memetic algorithm for multiple objective optimization with an industrial application [Journal of Heuristics] Vol.14 P.313-333 google
OAK XML 통계
이미지 / 테이블
  • [ Figure 1. ]  Random key representation encoding method.
    Random key representation encoding method.
  • [ Table 1. ]  Mean number of activities in each group of 4 processes
    Mean number of activities in each group of 4 processes
  • [ Table 2. ]  Experiment result
    Experiment result
  • [ Figure 2. ]  Generated process reference model using genetic algorithm approach (Yahya et al., 2010). PSM: proximity score measurement.
    Generated process reference model using genetic algorithm approach (Yahya et al., 2010). PSM: proximity score measurement.
  • [ Figure 3. ]  Some alternatives of process reference considering time <30. PSM: proximity score measurement
    Some alternatives of process reference considering time <30. PSM: proximity score measurement
  • [ Table 3. ]  Performance evaluations of three scenarios using MoMILP and MOBPGA
    Performance evaluations of three scenarios using MoMILP and MOBPGA